SCDOT proposes intersection improvements on SC 9 from I-85 to Shoally Creek Rd / 4th St intersections to include widening of SC 9 to add a third travel lane in each direction & adding/lengthening turn lanes along with reconfiguring 4th St at an existing sharp curve, & installing a traffic signal at SC 9 and Candlenut Ln.

The project is estimated to cost around $4.7 million which includes $700,000 for preliminary engineering, $1.2 million for right-of-way, and $2.8 million for construction.



Update (February 2020)

  • PE is 50% complete
  • ROW Acquisition is scheduled for Fall 2020
  • Construction Letting is scheduled for Fall 2021


Update (June 2019):

  • PE is approximately 30% complete
  • ROW Acquisition is scheduled for Fall 2020
  • Construction Letting is scheduled for Fall 2021


Update (November 2019):

  • PE is 40% complete.
  • ROW Acquisition is scheduled for Fall 2020.
  • Construction Letting is expected for Fall 2021.